Displaying overview of rejected materials
Menu path
Go to Manufacturing ➔ Statistics ➔ Rejected and click the Display button.
Introduction
Rejected
material is the excess amount of purchased material that is not used in the
production process and cannot be returned to stock. The overview of rejected
material displays key data for each production order, such as the excess quantity
and the cost involved. You can obtain an overview of rejected materials in this screen.
Columns
The
rejected material overview provides information on the end date of the
production order, the excess quantity rejected by production process, and the
cost of the rejected quantity.
Production orders
This
column displays the project numbers that are linked to the production
orders.
Description
This
column displays the descriptions of the production orders as filled in by you when
you created the production orders.
Item code
This
column displays the item codes of the finished items which have been taken into
production through the production orders.
Description
This
column displays the descriptions of the finished items which have been taken into
production through the production orders.
End date
This
column displays the end dates of the production orders as filled in by you when
you created the production orders.
Quantity
This
column displays the actual number of rejected units. The actual quantity is
calculated by comparing the units of materials issued to the units of finished
products that have been received. If the number of finished products received is
smaller than the number still to be received as per the production order
planning, then too much materials have been issued. As soon as you decide not to
return the excess material, the materials are then treated as
rejected.
Costs (EUR)
This
column displays the actual costs for the rejected materials by units. These costs
are calculated by multiplying the number of rejected units by the cost price of
the materials.
Buttons
Export
Click this to display the MRP overview in
Microsoft Excel.
Project
Click this to view the project card of the selected production
order.
Note:
This button is enabled only if you have the E-Project
module.
Production
Click this to view or modify a
production order in the Production
orders screen.
Close
Click this to exit.
Related document
Main Category: |
Attachments & notes |
Document Type: |
Support - On-line help |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
12.290.122 |
Assortment: |
Exact Globe+
|
Date: |
26-09-2022 |
Release: |
|
Attachment: |
|
Disclaimer |